Name of the client | Project description | Project period | Cost (In lakhs) |
---|---|---|---|
M/s Kusuma Bhandary Constructions Pvt Ltd. | Providing Pile foundations for Srinivas Medical college at Mukka. | May 10-Sept 10 | 43.3 |
M/s Lanco Infratech Limited. | Providing Piles and Pile caps for minor bridge near Kunigal under project 4-laning of NH-48 from Nelamangala to Devihalli. | Dec 09-Sept 10 | 43.73 |
M/s Ircon International Ltd. | Construction of Foundation and Substructures of Minor no. 332/1 on NH-48 in NMPR Project, Mangalore. | Dec 09-Sept 10 | 6.62 |
M/s Jampana Construction Pvt Ltd | Providing pile foundations for construction of KRDCL bridges in Gadag District. | Dec 09-July 10 | 13.27 |
M/s Sobha Developers Ltd. | Providing Pile foundations at Infosys Mysore HF Phase-III Block 5 & 6 Gymnasium Block. | Mar 10-Jul 10 | 2.55 |
M/s Rajshri Packagers Ltd. | Providing pile foundations for Warehouse, Pipe rack & weigh bridge at Baikampady. | Feb 10-June 10 | 11.48 |
M/s Ircon International Ltd. | Construction,installing and concreting of 750 mm dia bored cast-in-situ piles in foundations complete as per drawings and Technical Specifications at Kottara Flyover on NH-17 in NMPR Project. | Nov 09-Mar 10 | 22.8 |
M/s Rajshri Packagers Ltd | Providing Pile Foundations for Warehouse and Sub Station Building. | Aug 09 to Nov 09 | 15.36 |
M/s Rajshri Packagers Ltd. | Providing pile foundations for Crude oil tanks at Baikampady. | Sept 09 to Nov 09 | 19.35 |
M/s Akshaya homes Pvt. Ltd. | Providing pile foundations for your commercial complex Domaine at Karapakkam, Chennai. | Sept 09 to Nov 09 | 38.84 |
R.P Shiva, P.W.D. Contractor. | Providing pile foundations for railway station building at Thokur- Konkan Railway. | Jan 09 to May 09 | 37 |
M/s Nagarjuna Construction Company, Hyderabad. | Providing pile foundations for Main gate complex, Gymnasium for Seabird Project at Karwar. | Jan 09 to April 09 | 134 |
M/s Ircon International Ltd. | Construction of Pile Caps and Sub-structures of Minor Bridges excluding Superstructure at locations 370/4 & 365/1 on NH-17. | Feb 08 to April 09 | 9.71 |
M/s Ircon International Ltd.M/s Ircon International Ltd. | Construction of Pille Caps-P5,P6&P7 of BC Road flyover on NH-48 in NMPR Project, Mangalore. | Dec 08-Feb 09 | 2.55 |
Sobha Developers, Bangalore. | Providing pile foundations for Hostel block 5 & 6 for Phase III at Infosys, Mysore. | Jan 09 to Feb 09 | 7 |
M/s Ircon International Ltd. | Providing test piles at Surathkal, Maroli, Kuntikana & B.C.Road. | Nov 08 to Jan 09 | 3 |
M/s Ircon International Ltd. | Providing Initial, Routine & lateral load tests at various locations. | 2008-2009 | 9.5 |
Name of the client | Project description | Project period | Cost (In lakhs) |
---|---|---|---|
The Executive Engineer, Ports Division, Karwar. | Providing pile foundations of 600mm dia(Marine) for tidal observatory. | May 05 to Dec 05 | 23.13 |
M/s Tharaka Engineers, Mangalore. | Pile foundations for aquaduct of Haladi, Kundapur. | Jan 05 | 22.47 |
M/s Tharaka Engineers, Mangalore. | Strengthening of Lightrage Wharf at Karwar Port. | 2009 | 178 |
Name of the client | Project description | Project period | Cost (In lakhs) |
---|---|---|---|
The Executive Engineer,PWD, Udupi. | Malpe Fishing Harbour. Construction of fishing Harbour including dredging for slopes. | Jul 00 | 116 |
Director of Ports & IWT, Karwar. | Dredging at Kodibengre Harbour. | Mar 00 | 16 |
The Executive Engineer,PWD, Udupi. | Kodibengre Fishing Harbour, Karnataka. Construction of Fishing Harbour. | Jul 99 | 114 |
The Executive Engineer,PWD, Udupi. | Hejmadi Fishing Harbour, Karnataka. Construction of fisheries jetty including dredging of basin. | Sep 02 | 85 |
Advani Export Limited, Mumbai. | Pile foundation for Advani exports at Belekeri Port. | Mar 04 | 24 |
The Executive Engineer, Port & fisheries Division, Karwar. | Extensions of fisheries wharf at Karwar.Construction of fishing harbour including dredging. | Aug 04 | 127 |
Name of the client | Project description | Project period | Cost (In lakhs) |
---|---|---|---|
M/s Ircon International Ltd. | Development of adequate road connectivity to NMPT to B.C.Road on NH-48-Box Culverts. Open foundation, side walls and deck slab. | Nov 09 to Jun 10 | 13.97 |
M/s Ircon International Ltd. | Construction of ODC road for OMPL at Mangalore for MRPL. | Sept 09 to Mar 10 | 43.8 |
M/s Ircon International Ltd. | Development of Adequate Road connectivity to NMPT-Construction of Minor Bridges on NH-48. | Feb 09-Nov 09 | 11.48 |
K.T.Tandel, Karwar. | Construction of Radar tower (RCC-structure) at Karwar Port. | Nov 06 to March 07 | 7.72 |
Name of the client | Project description | Project period | Cost (In lakhs) |
---|---|---|---|
The Executive Engineer,Karnataka Urban Water Supply & DB, Bangalore. | Construction of footbridge across Alvekodi river & Konkan Valley under Honnavar water supply scheme. | Jun 99 | 22.81 |
Executive Engineer, Goa Central Division I CPWD, Bambolim, Goa. | Construction of office cum residential building for Passport Office. | Feb 00 | 63 |
Executive Engineer, Goa Central Division I CPWD, Bambolim, Goa. | Construction of office cum residential building for Registrar of Company. | Feb 00 | 46.25 |
The Executive Engineer,Karwar. | Administrator Building of the Director of Ports, Karwar. | Mar 00 | 60 |
M/s National Building Constructions Ltd., Kandla, Gandhidham. | Custom Quarters type iii building at Kandla, Gandhidham. | Mar 01 | 9 |
M/s National Building Constructions Ltd., Kandla, Gandhidham | Special Repair work at Kandla. | Jun 01 | 7.8 |
Port Engineer, Directorate of Ports & IWT, Karwar. | 50T Bollard at Karwar for wharf. | Oct 01 | 10.5 |